Sonotube Concrete Calculator
How the Calculator Works
The calculator uses one simple formula: radius times radius, times pi, times height.
That's it. That's the volume of any cylinder, and a Sonotube is just a cylinder. Here's what you enter:
Diameter in inches (this is how Sonotube sizes are listed), and height in feet (how tall your pour needs to be). The calculator then converts that number into cubic yards or a bag count, so you know exactly what to order.
Why Manual Estimates Go Wrong
Most concrete shortages come down to one of two mistakes.
Mistake #1: Using diameter instead of radius
The formula needs the radius, which is half the diameter. Skip that step, and your estimate comes out four times too high.
Mistake #2: Forgetting the tube gets cut
An 8-foot tube rarely gets poured at 8 feet. Once you factor in your footing depth and how much sticks out above ground, the real number is usually shorter. If you calculate using the full tube length instead of the actual pour height, you'll order too much.
Concrete Volume by Tube Size
Here's a quick-reference chart. Find your tube size, then multiply by how many feet you're pouring.
| Tube Diameter | Volume per Foot | 80 lb Bags per Foot |
|---|---|---|
| 8 in | 0.0349 cu yd | 0.65 |
| 10 in | 0.0545 cu yd | 1.02 |
| 12 in | 0.0785 cu yd | 1.47 |
| 16 in | 0.1396 cu yd | 2.61 |
| 18 in | 0.1767 cu yd | 3.31 |
| 24 in | 0.3142 cu yd | 5.88 |
Example: Pouring a 12-inch tube 4 feet deep? Multiply 0.0785 by 4. That's 0.314 cubic yards, or about 6 bags of 80 lb concrete.
Always Order a Little Extra
Even a perfect calculation won't match what actually gets poured. Concrete gets spilled. Holes are never perfectly even. Wet concrete pushes against the form and can bulge it slightly.
That's why most pros add 5 to 10% on top of the calculator's number. It's a small buffer that saves you a second trip to the store.
Got more than one pier? Run each one through the calculator separately instead of averaging them. Hole depths are rarely identical, and small errors add up fast across eight or ten footings.
Cubic Yards or Bags? Here's How to Decide
Cubic Yards
Use this if you're ordering from a ready-mix truck. Most suppliers have a 1 cubic yard minimum, so this only makes sense for bigger jobs.
Bag Count
Use this if you're mixing your own with bagged concrete. This works best for smaller jobs, usually under 1 to 2 cubic yards total.
Pick one method before you order. Mixing yards and bags in the same conversation with your supplier just leads to confusion.
Frequently Asked Questions
Bottom Line
A Sonotube calculator takes the guesswork out of ordering concrete. Plug in your tube size and height, add a little extra for waste, and you'll know exactly what to buy before you start digging.